891 | PETROGAZ ENGINEERING SDN BHD | 2019-07-31 | Construction | Ipoh Sessions Court | Sec. 10(c), AKJ 1967. Failing to ensure that every working floor for open edges is constructed safely to prevent the risk of persons falling. | RM30,000 | SILVER |
892 | PETROGAZ ENGINEERING SDN BHD | 2019-07-31 | Construction | Ipoh Sessions Court | Reg. 5(1)(a)(aa) – OSH Regulations (NADOPOD) 2004, AKKP1994. Failed to immediately notify the nearest OSH office by the quickest means available and within 7 days to submit a report in the approved form of a fatal accident. | RM5,000 | SILVER |
893 | PETROGAZ ENGINEERING SDN BHD | 2019-07-31 | Construction | Ipoh Sessions Court | Sec. 10(c), AKJ 1967. Failing to ensure that every working floor for open edges is constructed safely to prevent the risk of persons falling. | RM30,000 | SILVER |
894 | PESONA METRO SDN. BHD. | 2019-11-14 | Construction | Magistrate's Court Three (3), Shah Alam | Reg. 5(1)(a)(aa) – OSH Regulations (NADOPOD) 2004, AKKP1994. Failed to immediately notify the nearest OSH office by the quickest means available and within 7 days to submit a report in the approved form of a fatal accident. | RM2,000 | SELANGOR |
895 | RINGLET JAYA COMPANY SDN. Ltd. | 2021-01-26 | Construction | Raub Sessions Court | Sec. 15(1), OSHA 1994. Employer failed to ensure that arrangements were made to ensure, so far as practicable, safety and the absence of risk to health in connection with the use or operation, handling, storage and transportation of plant and materials for construction including studying the stability of soil structures on hillsides in accordance with the designs of a Professional Engineer. | RM20,000 | PAHANG |
896 | MEKASSAR COMPANY (M) SDN. Ltd. | 30/4/2025 | Manufacturing | Rompin Magistrate's Court | Reg. 5(2), OSH Regulations (NADOPOD) 2004, OSH 1994. Failing to submit within seven (7) days a report of an accident or dangerous occurrence in the approved form to the OSH regarding an accident of an employee resulting in the inability to carry out his/her normal work for more than four (4) calendar days. | RM1,000 | |
897 | MEKASSAR COMPANY (M) SDN. Ltd. | 2019-10-21 | Manufacturing | Kuantan Sessions Court | Sec. 15(1), OSHA 1994. The employer failed to ensure, so far as is practicable, the safety, health and welfare at work of all his employees by establishing Safe Working Procedures (SWP) for the repair of derailment cages. | RM15,000 | PAHANG |
898 | Kosinar Enterprises Sdn Bhd | 2018-09-24 | Manufacturing | Kota Kinabalu Sessions Court | Section 15. AKJ 1967. Failure to install a strong fence around dangerous machinery | RM10,000.00 | Sabah |
899 | PERUSAHAAN KAYU PAHANG TIMUR | 2025-02-27 | Manufacturing | Kuantan Magistrate's Court | Reg. 4(7), OSH Regulations (NE) 2019, OSH Act 1994. Employer fails to implement recommendations for any action in the noise risk assessment report. | RM3,000 | |
900 | KAA CONSULTING SDN BHD | 2019-09-11 | Construction | Georgetown Sessions Court | Sec. 15(1), OSHA 1994. Employer failed to ensure, so far as practicable, the safety, health and welfare at work of all his employees in carrying out engineering calculations for temporary slopes resulting in landslides. | RM40,000 | P.PENANG |